With great vision, courage, and enthusiasm, ARAMICO is developing the technical knowledge for many different processes in the field of mining and metallurgy, and with years of testing and research on the production of high-purity copper, cathodes established ITAD in 2016.

Copper Section

2022

Start testing and operating capacity measurement of equipment

2020

Purchase of the land and starting construction of the production line (leaching, SX, and EW)

2019

Buying mines in Zanjan province

2018

Carrying out additional research for continuous vat Leaching and tubular EW cell processes

2015

Pilot implementation of the SX and EW processes

2014

Basic tests for cathode copper production

2022

Start testing and capacity measurement of equipment

2020

Purchase of land and start of operational operations of copper cathode production to Leaching-SX-EW

2019

Buying mines in Zanjan province

2018

Additional research for Continues VAT Leaching and Tubular EW Cell processes

2015

Implementation of the SX-EW pilot

2014

Basic tests for cathode copper production